HomeNewsHinkley project meets key milestone as high voltage cables installed under Mendips

Hinkley project meets key milestone as high voltage cables installed under Mendips

-

National Grid and Balfour Beatty engineers working on the Hinkley Connection Project have completed the installation of high voltage, 400kV cables under the Mendip Hills.

Since starting in February 2021, teams have pulled a total of 102km cables (the distance between Bridgwater and Gloucester).

They say the cables were delivered on 108 separate cable drums. Each drum held approximately 1km of cable, weighed between 35-50 tonnes, and stood 5 metres high.

Next follows a programme of jointing and testing with energisation expected in Autumn this year.

Reinstatement of the land is already underway on different parts of the route.  The Mendip cables section of the Hinkley Connection Project will be fully complete by the end of 2023.

Once work is completed and existing WPD pylons removed in summer, this part of the Mendip Hills AONB will be pylon free for the first time since the 1960s.

Last week, representatives from the AONB Unit visited to see the works for themselves and gain insight into what is involved in a project of this scale.

Jim Hardcastle, Manager of the Mendip Hills AONB Unit, says: “Placing the cables underground clearly requires complex engineering solutions but it also reinforces the importance of the AONB status.”

“The status recognises the Mendip Hills as one of England’s finest landscapes and loved by many people. Organisations should go above and beyond the normal levels of delivery in such a special place like this.”

“The visit helped our understanding a lot so we can transfer this to others who ask us about it – especially the reinstatement after the work is completed.”

James Goode, Project Director for National Grid, adds: “Completion of the installation underground cables in the Mendip Hills is a huge milestone for the project, bringing us a step closer to bringing low carbon energy to 6 million homes and businesses across the UK.”

“The project continues with construction of pylons – including the world’s first T-pylons – along the route between Hinkley Point C and Seabank substation, with completion due in 2025.”

“We want to be a good neighbour and work with local charities and organisations like the Mendip Hills AONB Unit along the route of our project, supporting initiatives like Counting on Mendip and other projects.  We were delighted to welcome the AONB Unit onto site to see the works at first hand.”

Pictured: The Mendip Hills Unit visit to learn more about the work. From back: Jim Hardcastle, Manager of the Mendip Hills AONB Unit, Tim Haselden, Development Officer and Judith Chubb-Whittle, Landscaping Officer for the Mendip Hills AONB at a joint bay where sections of the 400kV cables are connected together

TODAY'S MOST VIEWED NEWS

WEATHER

Burnham-on-Sea
broken clouds
7.7 ° C
7.8 °
6.2 °
99 %
3.5kmh
64 %
Thu
11 °
Fri
11 °
Sat
9 °
Sun
10 °
Mon
11 °